The Ross Ceramics projects involved work across several blocks at the Stoke on Trent depot.
The project included the removal of existing asbestos cement sheeting, which was replaced with Joris Ide composite roof sheets and triple skin GRP composite roof lights, enhancing the influx of natural daylight into the space by 10%.
Stoke on Trent
The project then progressed to block B, where the canopy area was stripped, enabling the installation of single skin roof sheets and natural daylight roof sheets.
Subsequently, Blocks C, D, and E, which encompass the large manufacturing areas at the site, were fitted with Factory clad fire-rated insulation, followed by the installation of new single skin roofing sheets and roof lights.
The project concluded with the installation of new gutter lining, covering approximately 380 linear meters, to prevent any future gutter leaks.